We can all take a deep breath before the James Webb Space Telescope’s next major deployment.
On Tuesday (Jan. 4), Webb finished bringing its huge, five-layer sunshield up to the proper tension, wrapping up the most complex and tricky operation of the $10 billion observatory’s lengthy deployment phase.
The mission team can therefore now turn to the next big-ticket item on its to-do list: getting the telescope’s secondary and primary mirrors into the proper configuration. But it’ll take a while to check those boxes.
Related: Building the James Webb Space Telescope (gallery)
“So I would say probably by this weekend we will start that process,” Alphonso Stewart, James Webb Space Telescope deployment systems lead at NASA’s Goddard Space Flight Center in Greenbelt, Maryland, said during a news conference on Tuesday. “But then it runs for about 10 days. That whole mirror deployment is a 10-day period.”
Webb’s 21.3-foot-wide (6.5 meters) primary mirror consists of 18 hexagonal segments arrayed across a central platform and two smaller side “wings.” These wings were folded back prior to launch so the assembly could fit inside the protective payload fairing of Webb’s Ariane 5 rocket. (The sunshield is about the size of a tennis court, so it too had to unfurl after liftoff.) Deployment of the primary mirror involves extending the two wings and locking them in place.
Webb’s secondary mirror is so named because it’s the second surface, after the primary, that light will hit on its way into the telescope’s four science instruments. The 2.4-foot-wide (0.74 m) secondary mirror sits at the end of several booms, which must be extended.
The secondary mirror will be deployed first. Although that operation is still a few days away, the Webb team plans to get the ball rolling on it very soon.
“Starting tonight, we’ll start heating the motors that deploy the secondary mirror structure,” Stewart said during Tuesday’s news conference. “Following that, the next two days, we’ll start heating [motors] in preparation for the wing mirror deployments.”
Webb mission team members have stressed repeatedly since the observatory’s Dec. 25 launch that most deployment operations are flexible, so don’t be surprised or overly concerned if there are some deviations from the timeline laid out above.
Webb is designed to pick up faint heat signals from the early universe, challenging work that requires its optics and instruments to remain extremely cold. That’s why the observatory has such a big sunshield and why it will operate at the Earth-sun Lagrange Point 2 (L2), a gravitationally stable spot about 930,000 miles (1.5 million kilometers) from our planet. At L2, Webb will stay aligned with Earth, the sun and the moon, allowing the sunshield to block light and heat from these bodies continuously.
If all goes according to plan, the telescope will slip into orbit around L2 with an engine burn 29 days after launch (on Jan. 23). At that point, Webb will be at its final destination with all major deployments complete. But the observatory won’t be ready to begin its science work yet.
The mission team will still need to align the 18 primary mirror segments precisely so they act as a single light-collecting surface and check out and calibrate Webb’s instruments. These jobs will take several months to complete. Science operations are expected to begin this summer and last at least five years.